Build a practical HDB renovation schedule around approvals, trade dependencies, deliveries and a proper handover.
When can the hacking start? When should the appliances arrive? When is it safe to book the movers? A useful renovation schedule answers all three by showing what needs to happen before each trade can start. It should also separate the overall project timeline from the window allowed for any permit-controlled work.
01. Set the dates that control the job

Start with the date you can access the flat, the intended site start and the target handover. Work backwards from handover to set deadlines for drawings, tiles, fittings and appliances. Confirm who is ordering each item, when it needs to arrive and which trade needs it.
HDB requires a permit for certain works. Ask your contractor to identify those items, check the dates and conditions of the issued permit, and plan the required notices to neighbours. Put design work and off-site orders on the overall schedule separately from work governed by the permit.
02. Protect the flat before hacking begins

Walk through the flat with your contractor and identify what is staying, what is being removed and which surfaces need protection. For a resale flat, leave room in the schedule for a site check once finishes are opened up. If the team discovers an issue, ask for the revised scope and timing before the next trade starts.
HDB applies tighter hours and day restrictions to noisy renovation works than to general renovation. Ask for the actual dates of any approved hacking and check them against the permit conditions and HDB guidance.
03. Coordinate concealed work, waterproofing and tiling

Have the designer, plumber and electrician confirm fixture locations, appliance requirements and cable or pipe routes before surfaces are closed up. For each bathroom, ask the contractor to show where waterproofing, its required checks and any curing time fit before tiling proceeds.
The order can differ by room and by the system being installed. Ask which areas can progress in parallel and which must wait for a check or sign-off. Record these dependencies on the schedule so a delay is visible before the next crew turns up.
04. Separate carpentry measurement, fabrication and installation

Give carpentry three separate dates. Site measurement confirms the dimensions the workshop will build to. Drawing sign-off confirms the layout, finishes and appliance clearances. Installation depends on both workshop completion and the site being ready.
Ask when the countertop supplier will measure and whether it needs the base cabinets in place first. Confirm the sink, hob and appliance dimensions before the workshop commits to cut-outs or cabinet openings.
05. Schedule fittings and deliveries around site readiness

Confirm which trades are returning to connect lights, switches, sanitary fittings and appliances. Keep owner-supplied items on the same schedule. For example, a sink arriving after the booked installation slot can push back the plumbing connection and the final checks.
Set delivery dates against the point when rooms are clean and ready to receive items. Ask who will test each fitting, who handles packaging removal and when any final paint touch-ups will happen.
06. Allow time for inspection and rectification

Put a joint walkthrough on the calendar before the intended move-in. Check the agreed scope room by room, test accessible fittings and record items that need attention with a location, a responsible party and a target date.
Keep inspection, rectification and handover as separate milestones. When dates shift, ask for an updated schedule that shows which later tasks are affected. Leave time between the walkthrough and your movers if your housing arrangements allow.
For the current requirements, refer to HDB’s renovation permit guidance and renovation rules and work timings. CCS also shares guidance on agreeing a written renovation schedule.
If you are planning an HDB renovation, share your floor plan and target move-in date with Formstill Studio. We can discuss the work sequence and the decisions that affect your schedule.
For information and reference only. The scope, methods and sequence for your renovation depend on actual site conditions, applicable requirements and the on-site assessment and professional judgement of the specialists carrying out the work.
